Passing lanes being introduced at highways 9 and 10 near Yorkton

Work will start this fall on passing lanes between Melville and Yorkton, and Yorkton and Canora on Highways 10 and 9.

The cost of the project is about $34.9 million with a scheduled completion date of October 15, 2020.

It will see six passing lanes built, along with intersection improvements and realignments, access consolidation, 55 km of resurfacing, replacement and upgrading of a significant number of culverts, and intelligent transportation systems such as weather monitoring sensors.