COVID-19; Co-op Refinery delays turnaround until at least May 15th

Like many others, the Co-op Refinery Complex is doing what they can to try and slow down the spread of COVID-19.

On Tuesday CRC announced that its annual turnaround will be delayed until at least May 15th.

The annual mega project was supposed to begin at the start of April.

Turnaround typically sees an influx of hundreds of additional workers on site at CRC.

The CRC has put a Business Continuity Plan (BCP) in place that incorporates best practices in pandemic planning
and will continue to consult with health care officials to monitor and prevent the spread of COVID-19.