REGINA — Construction season is underway in Regina. Here are some traffic tips for drivers, according to the City of Regina's website.
Lakeview Avenue – Queen Street to McIntosh Street
Monday, June 7 should be the last day of a full road closure to complete concrete replacement and paving. Work began April 27.
Walden Crescent – Cambridge Avenue to Glencairn Road
Until June 12, there will be lane restrictions for crews to repair concrete and pavement. Work began April 27.
Here are some longer-term restrictions:
11th Avenue Revitalization Project
Residents should expect moving traffic restrictions along 11th Avenue as work moves east to west beginning on Scarth Street.
Lakeview Avenue – Queen Street to McIntosh Street
Until June 8, there will be a full road closure to complete concrete replacement and paving. Work began April 27.
Sherwood Drive – 7th Avenue North to Williston Drive
Until June 24, there will be lane restrictions to allow for pavement repairs. This will be a phased approach to allow for better traffic flow. Work started April 27.
Froom Crescent – Vaughn Street to Cushing Crescent
Until July 3, there will be lane restrictions for open pits to reline existing watermains. Lane restrictions will only occur around the pits. Work began April 28.
Wascana Street – 17th Avenue to 19th Avenue
Until July 24, lane restrictions will occur to reline a watermain. Work began May 11.
McCarthy Boulevard – Mikkleson Drive to 4th Avenue
Until July 31, there will be lane restrictions to allow crews to clean and reline a sewer main. See Regina.ca/Southwest for details. Work started April 27.
Reynolds Street – 19th Avenue to Broadway Avenue
Until Aug. 28 at 5 p.m. there will be road closures on a block-by-block basis to install new storm water mains, water main replacement, curb and sidewalk replacement and roadway reconstruction. Work began March 30.
College Avenue – Angus Street to Albert Street
Until Aug. 31 there will be a lane restriction on the northside curb lane. Work began March 20.
Broadway Avenue – Francis Street to Edgar Street
Until Sept. 7, lane restrictions will occur to complete drainage work. Work began May 11.
11th Avenue – McIntyre to Albert Street
Until Oct. 30, 11th Ave from McIntyre to Albert St will be closed to complete water and roadways work as part of the 11th Avenue Revitalization Project. Work began May 12.
Albert Street North – Bridge over Ring Road
Until Oct. 31 two-way traffic will be diverted to the southbound bridge for bridge reconstruction. The northbound exit ramp onto Ring Road eastbound will also be closed. Work began March 23.